Wednesday, October 28, 2009

Skyview

Quite a bit of action since last time even though it rained (again). First the flatwork was done in the front and the back. We removed one step, added another one based on the actual ground level...





Two views on the back, with the porch and the kitchen sliding doors




Also on the roof side, the cathedral ceiling area is now in progress and it is quite fun the see:






This is  how it looks like a few days ago (with more sun and daylight).

 

Lastly for today the rear porch is getting some cover as well as pictured here:




Wednesday, October 14, 2009

Dressing-up

Maybe not in time for the rain, but still getting some shape after all..




The see-through style is now not there anymore...



Tuesday, October 13, 2009

Card Castle

Still going, almost done but still a one or two weeks away from a roof I'm afraid.






These are two views of the master bedroom.

Saturday, October 3, 2009

Up again

The building of the second level appears to be relatively faster that the first one, but there is still a lot of work. We are now 3 months into the construction and the progress appears quite good. The important thing being to have a roof before the rainy season...
The picture below shows the soon to come stairs.



 Now this picture show the master bedroom (you'd have guessed I'm sure...).