Saturday, May 29, 2010

Wait and see...

We've just suffered our most painful delay as it required 3 weeks to get the hardwood floor to 1.5 % of humidity level compared to the sub floor. They started with an amazing 6% difference and now we are ready to see the progress but it's been a little hard. In the meantime some things moved, but not as much as we'd wanted. Our goals to get back in the house in June appears harder and harder to keep.


Also we've been working with hardwood floor installer to find a solution to nicely finish the part of the floor that goes underneath the sheet-rock and this is what he came up with. Not exactly what we wanted but a nice compromise that should last a long time.


Also a few more pictures of things that are moving:







 The cooktop looks terrific. We did not know really what a yellow-ish top would do but it turned out awesome...


And to finish some exterior work (actually done some time ago) with a garage door....


Thursday, May 13, 2010

Stairs and Colors...

Finally we have some colors - white is done and walls got one coat of paint for now.


Also the hardwood floor work is starting with the stairs in order to get the hand rail installed.



Wednesday, April 28, 2010

Vanity?

We now have the  kids' vanity looking like this - ready for plumbing.



 and the downstairs one is looking like this:



A vessel (and faucet) will come in later...

In the garage some action as well, with the water heater and furnace in place. They haven't been started yet but they are in..

Friday, April 23, 2010

Kitchen Countertop, done.

Finish look is really good and we can't wait for the floor and paint to be done now...




Tuesday, April 20, 2010

Kitchen and bath racing towards the finish line

First appearance of the countertop surface in the kitchen - it is a ceasarstone quartz reflexion, pretty cool, it is basically quartz and some pieces of recycled glass inside, small ones just to give some sparkle.


Half of it is done, still working on the island, which is the tricky part. We were a little concerned about the seams which are located on both sides of the cooktop. But it's really not an issue as you can see here it is really hard to find it:



Next is the fact that the painskating hours we spent choosing the plumbing appliances are starting to pay off somehow...






Sunday, April 18, 2010

Ups and Downs...

Funny to see that it appears to move by bursts and last week was not really one. Not saying that it did not move but what happened was not as visible as I would expect...anyway:

Some action in the kitchen with the fridge getting very close to being in place:


 Now back to the bathrooms with most of the tile done (including the floor ones):



As you can see the master bathroom vanity got some granite cover as well.

Monday, April 5, 2010

Major finish actions, yeah!

Things come to those who wait...we're supposed to know. Well it is happening to us right now! Quite a bit of excitement on this beginning of week with major action going on in the bathrooms.

First the guest bathroom got tiles and a vanity, yes!. The vanities in the house are built by the cabinet maker of our contractor and after discussing plans we finally discovered them today. They're great I have to say and very close to what we had hope for...always nice isn't...








Now the kids bathroom. Barely starting the tiles, but the vanity is in. This one is attached on three sides somehow...




And finally, the master bathroom if seeing some action: